Week of September 15, 2019

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

 ROUTE 29 / GAINESVILLE

I-66 East and West from Route 29 Gainesville to Route 234 Business (Sudley Rd)

Monday, September 16 – Thursday, September 19: 11 a.m. to 12 p.m.

Virginia State Police will pace eastbound and westbound traffic in this area to a slow roll, with temporary stoppages possible, for blasting operations along I-66 between University Boulevard and Prince William Parkway. Slow roll conditions should last for approximately 15 minutes. Additionally, stoppages will also occur on northbound Prince William Parkway (Route 234 Bypass) just north of the exit to I-66 East and from Route 29 in Gainesville to I-66 East starting at 11 a.m.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 East from Route 234 Business to Route 29 Centreville

Sunday, September 15: 9 p.m.to 5 a.m.

Monday, September 16 – Thursday, September 19: 7 p.m. to 5 a.m.

Friday, September 20 – Saturday, September 21: 10 p.m. to 8 a.m.

Two lanes closed for paving operations. 

 I-66 West from Route 29 Centreville to Route 234 Business

Sunday, September 15: 9 p.m.to 5 a.m.

Monday, September 16 – Thursday, September 19: 9 p.m. to 10 a.m.

Friday, September 20 – Saturday, September 21: 10 p.m. to 8 a.m.

Two lanes closed for paving operations. 

 ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 West at  Route 28

Ramp from I-66 West to Route 28 South

Sunday, September 15 – Thursday, September 19: midnight to 5:30 a.m.

There will be a full closure of I-66 West at Route 28 each night for crews to lift bridge beams into place over I-66. The ramp from I-66 West to Route 28 South will also be closed.  Traffic will be detoured to Route 28 North to Westfields Boulevard westbound, then stay to the right for Route 28 South. Traffic can then follow signs to return to I-66 West or continue south on Route 28.

Compton Road at I-66

Monday, September 16 – Friday, September 20: 9 p.m. to 5 a.m.

Occasional 20-minute stoppages on Compton Road under I-66 as crews perform bridge demolition in preparation for the new lanes on I-66.

 I-66 East from Route 234 Business to Route 29 Centreville

Sunday, September 15: 9 p.m.to 5 a.m.

Monday, September 16 – Thursday, September 19: 7 p.m. to 5 a.m.

Friday, September 20 – Saturday, September 21: 10 p.m. to 8 a.m.

Two lanes closed for paving operations. 

 I-66 West from Route 29 Centreville to Route 234 Business

Sunday, September 15: 9 p.m.to 5 a.m.

Monday, September 16 – Thursday, September 19: 9 p.m. to 10 a.m.

Friday, September 20 – Saturday, September 21: 10 p.m. to 8 a.m.

Two lanes closed for paving operations. 

 ROUTE 286 (FAIRFAX COUNTY PARKWAY)

No significant traffic impacts scheduled.

 ROUTE 50 / FAIRFAX

No significant traffic impacts scheduled.

 ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

No significant traffic impacts scheduled.

 ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 West from Gallows Road to Nutley Street

Saturday, September 14: 9:00 p.m. to 9 a.m.

Three lanes will be closed on I-66 West for crews to shift traffic on I-66 near Vaden Drive. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66 and on the ramp from Virginia Center Boulevard to I-66 West.

 I-495 (CAPITAL BELTWAY)

I-66 West from I-495 to Gallows Road

Ramp from I-495 North Express Lanes to I-66 West

Sunday, September 15– Friday, September 20: 9 p.m. to 5 a.m.

Two left lanes closed on westbound I-66 for new Gallows Road bridge construction in center median.  The ramp from the northbound I-495 Express Lanes to westbound I-66 will be closed nightly.  I-495 Express Lane North traffic will be detoured to the exit for I-66 East to the Route 7 (Leesburg), take a left off the exit and stay to the right to follow signs to I-66 West.