Week of November 4, 2018

The following planned lane closures are expected to have significant traffic impacts.  All work is subject to change based on weather and schedule.  Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.


ROUTE 234 (SUDLEY ROAD) / MANASSAS

Ramp from Sudley Road (Route 234) North to I-66 East

Sunday, November 4: 8 p.m. to 5 a.m.

Temporary narrowing of the ramp from northbound Sudley Road (Route 234) to eastbound I-66.  Drivers should expect occasional 20-minute stoppages and slowdowns on the ramp.

I-66 East from Sudley Road (Route 234) to Bull Run

Monday, November 5: 8 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

Ramp from Sudley Road (Route 234) South to I-66 West

Tuesday, November 6: 9 p.m. to 5 a.m.

Temporary narrowing of the ramp from southbound Sudley Road (Route 234) to westbound I-66.  Drivers should expect occasional 20-minute stoppages and slowdowns on the ramp.

I-66 West from Compton Road to Bull Run

Wednesday, November 7: 9 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 West from Compton Road to Bull Run

Wednesday, November 7: 9 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

I-66 East from Fairfax County Parkway (Route 286) to US Route 50

Monday, November 5 – Tuesday, November 6: 9 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-66 West from Chain Bridge Road (Route 123) to Monument Drive

Wednesday, November 7 – Thursday, November 8: 9:30pm to 5 a.m.

Friday, November 9 – Saturday, November 10: 9 p.m. to 9 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 50 / FAIRFAX

I-66 East from Fairfax County Parkway (Route 286) to US Route 50

Monday, November 5 – Tuesday, November 6: 9 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-66 West from Chain Bridge Road (Route 123) to Monument Drive

Wednesday, November 7 – Thursday, November 8: 9:30pm to 5 a.m.

Friday, November 9 – Saturday, November 10: 9 p.m. to 9 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

Ramp from Chain Bridge Road (Route 123) North to I-66 East

Tuesday, November 4: 9 p.m. to 5 a.m.

Temporary narrowing of the ramp from northbound Chain Bridge Road (Route 123) to eastbound I-66.  Drivers should expect occasional 20-minute stoppages and slowdowns on the ramp.

I-66 West from Chain Bridge Road (Route 123) to Monument Drive

Wednesday, November 7 – Thursday, November 8: 9:30pm to 5 a.m.

Friday, November 9 – Saturday, November 10: 9 p.m. to 9 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 East from Nutley Street to I-495

Sunday, November 4: 8 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-66 West from I-495 to Nutley Street

Monday, November 5: 9:30 p.m. to 5 a.m.

Thursday, November 8: 9:30 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

I-495

I-66 East from Nutley Street to I-495

Thursday, November 1: 9 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-66 West from I-495 to Nutley Street

Monday, November 5: 9:30 p.m. to 5 a.m.

Thursday, November 8: 9:30 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.