The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

I-66 East from Route 29 Gainesville to University Boulevard

Monday, November 25 – Tuesday, November 26: 9 p.m. – 5 a.m.

Three right lanes closed for demolition work on the University Boulevard bridge over I-66.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 East and West between Sudley Road and Bull Run Rest Stop

Sudley Road North and South at I-66

Monday, November 25 – Wednesday, November 27: 11 a.m. to 12 p.m.

Virginia State Police will pace eastbound and westbound traffic in this area to a slow roll, with temporary stoppages possible, for blasting operations along I-66. Slow roll conditions should last for approximately 15 minutes. Additionally, stoppages will also occur on northbound and southbound Sudley Road prior to I-66 starting at 11 a.m.  Stoppages may also be needed on Vandor Lane.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

No significant traffic impacts scheduled.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

No significant traffic impacts scheduled.

ROUTE 50 / FAIRFAX

No significant traffic impacts scheduled.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

No significant traffic impacts scheduled.

ROUTE 243 (NUTLEY STREET) / VIENNA

Ramp from I-66 West to Country Creek Drive

Westbound I-66 Collector-Distributor Lane at Vaden Drive

Starting at 9 p.m. Friday, November 22 through 5 a.m. Monday, November 25

Weekend closure of the ramp from I-66 West to Country Creek Drive for demolition work on Vaden Drive bridge. Additionally, the westbound collector-distributor lane will be closed prior to Vaden Drive. Traffic entering westbound I-66 from Nutley Street or Virginia Center Boulevard will merge into the I-66 West main lanes at the Vienna Metro Station.

I-66 West from Cedar Lane to Vaden Drive

Friday, November 22 – Saturday, November 23: 9 p.m. to 9 a.m.

Sunday, November 24: 9 p.m. to 5 a.m.

Three right lanes closed on westbound I-66 for demolition work at Vaden Drive.  I-66 West will be reduced to one left lane between 11 p.m. and 6 a.m. (until 4 a.m. Sunday p.m./Monday a.m.).

I-495 (CAPITAL BELTWAY)

I-66 West from I-495 to Gallows Road

Ramp from I-495 North Express Lanes to I-66 West

Monday, November 25 – Tuesday, November 26: 9 p.m. to 5 a.m.

Left lane closed on westbound I-66 for new Gallows Road bridge construction in center median.  The ramp from the northbound I-495 Express Lanes to westbound I-66 will be closed nightly.  I-495 Express Lane North traffic will be detoured to the exit for I-66 East to the Route 7 (Leesburg), take a left off the exit and stay to the right to follow signs to I-66 West.