Week of November 22, 2020

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

 

ROUTE 29 (LEE HIGHWAY) / GAINESVILLE

I-66 East from Route 29 (Lee Highway) Gainesville to Route 234 (Prince William Parkway)

Friday, November 20: 9 p.m. to 8 a.m.

Three right lanes will be closed for crews to relocate barrier and to implement a traffic shift on the collector-distributor lane.

 

Ramp from I-66 East to Route 234

Friday, November 20: 9 p.m. to 9 a.m.

Saturday, November 21: 11 p.m. to 6 a.m.

The ramp will be closed. Traffic will be detoured farther east to Route 234 Business South, turn right on to Balls Ford Road, then travel about two miles west to Route 234.

 

Ramp from Route 29 North Gainesville to I-66 East

Friday, November 20: 9 p.m. to 8 a.m.

The ramp will be reduced to one travel lane for crews to implement a traffic shift.

 

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

Ramp from I-66 West to Route 234 Business North

Starting at 10 p.m. Friday, November 20, through 5 a.m. Monday, November 23

The ramp will be closed. Traffic will be detoured to Route 234 Business South, continue to the intersection with Balls Ford Road, stay to the left and make a U-turn from the left-most left turn lane at the traffic signal on to Route 234 Business North.

 

I-66 West from Cub Run to Bull Run Drive

Monday, November 23, and Tuesday, November 24: 9 p.m. to 6 a.m.

Two lanes will be closed for overhead bridge work.

 

I-66 West from Route 234 Business (Sudley Road) to Groveton Road

Monday, November 23, and Tuesday, November 24: 8 p.m. to 5 a.m.

Three lanes closed for crews to implement traffic shift.

 

I-66 West from Cub Run to Route 234 Business

Ongoing

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Weekdays between 5 a.m. and 9:30 p.m. daily, three travel lanes will be open to traffic. Either two lanes will be closed between 9:30 p.m. and 5 a.m. nightly, leaving two travel lanes open, or three lanes will be closed between 10 p.m. and 5 a.m. nightly, leaving one travel lane open.

 

I-66 West from east of Route 29 Centreville to Cub Run

Ongoing

The HOV lane will be closed for paving operations.

 

ROUTE 29 (LEE HIGHWAY) / CENTREVILLE

I-66 East at Compton Road

Starting at 1 p.m. Saturday, November 21, through 6 a.m. Sunday, November 22

One lane will be closed for bridge work on Saturday, November 21 from 1 p.m. to 8 p.m. beginning at 8 p.m. Saturday night, November 21, through 6 a.m. Sunday, November 22 two lanes will be closed.

 

I-66 East from Compton Road to Route 29 Centreville

Monday, November 23, and Tuesday, November 24: 8 p.m. to 5 a.m.

Three lanes closed for crews to implement a traffic shift.

 

Ramp from I-66 East to Route 29 Centreville

Sunday night, November 22: Midnight to 4 a.m.

Monday, November 23, and Tuesday November 24: 10 p.m. to 4 a.m.

The ramp will be closed. Traffic will be detoured farther east to Route 286 (Fairfax County Parkway) North, stay to the right for I-66 West, then follow signs to Route 29. 

 

Ramp from Route 29 North and South Centreville to I-66 East

Monday, November 23, and Tuesday November 24: 10 p.m. to 4 a.m.

The ramp will be closed. Traffic on northbound Route 29 will be directed to continue to Route 28 interchange, take exit to Route 28 North, and then exit to I-66 East.  Traffic  on southbound Route will be directed to U-turn at Stone Road onto Route 29 North, continue to Route 28 interchange, take exit to Route 28 North, and then exit to I-66 East. 

 

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Braddock Road between Newton Patent Drive and Route 28

Monday, November 23, through Wednesday, November 25: 11 a.m. to noon

Temporary 15-minute stoppages of traffic for blasting operations.

 

I-66 East at Route 29 Centreville

Ongoing

The HOV lane will be closed for paving operations.

 

I-66 West from Cub Run to Route 234 Business

Ongoing

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Weekdays between 5 a.m. and 9:30 p.m. daily, three travel lanes will be open to traffic. Either two lanes will be closed between 9:30 p.m. and 5 a.m. nightly, leaving two travel lanes open, or three lanes will be closed between 10 p.m. and 5 a.m. nightly, leaving one travel lane open.

 

I-66 West from east of Route 29 Centreville to Cub Run

Ongoing

The HOV lane will be closed for paving operations.

 

ROUTE 28 (SULLY ROAD) / CENTREVILLE

Route 28 North and South between E.C. Lawrence Park and Westfields Boulevard

Sunday, November 22, through Tuesday, November 24: 9 p.m. to 5 a.m.

Two lanes will be closed for overhead bridge work at Poplar Tree Road.

 

Route 28 North from I-66 to Walney Road

Tuesday, November 24: 9 p.m. to 5 a.m.

Two lanes closed for crews to implement traffic pattern change and new ramp openings.

 

Ramp from I-66 East to Route 28 North

Tuesday night, November 24: midnight to 4 a.m.

The ramp will be closed. Traffic will continue on I-66 East, take the exit for Fairfax County Parkway North, stay to the right to follow signs to I-66 West, and then exit to Route 28 North.

 

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Braddock Road between Newton Patent Drive and Route 28

Monday, November 23, through Wednesday, November 25: 11 a.m. to noon

Temporary 15-minute stoppages of traffic for blasting operations.

 

Route 28 North at I-66

Ongoing

The right lane of Route 28 North at I-66 will remain closed to provide an extended merge lane for the ramp from I-66 East to Route 28 North.

 

ROUTE 286 (FAIRFAX COUNTY PARKWAY) / FAIR LAKES

West Ox Road South between Fair Lakes Parkway and Maze Lane

Wednesday, November 18, through Friday, November 20: 8 a.m. to 3 p.m.

Two right lanes will be closed for utility and paving work.

 

Stringfellow Road North and South at I-66

Monday, November 23, through Wednesday, November 25: 9 a.m. to 5 p.m., and 9 p.m. to 5 a.m.

The right lane will be closed bridge work.

 

I-66 West from Route 50 to Route 286

Ongoing

The HOV lane will be closed for roadway widening work.

 

I-66 East from Monument Drive to Waples Mill Road

Ongoing

The HOV lane will be closed for bridge work.

 

ROUTE 50 / FAIRFAX

I-66 East and West between Route 123 and Route 50

Monday, November 23, and Tuesday, November 24: 9:30 p.m. to 4:30 a.m.

I-66 East will be reduced to a single travel lane approaching Jermantown Road during the overnight hours Monday, November 23 and Tuesday, November 24 from 10 p.m. to 4:30 a.m. nightly. I-66 West will be reduced to a single travel lane approaching Jermantown Road during the overnight hours Monday, November 23 and Tuesday, November 24 from 9:30 p.m. and 4:30 a.m. nightly. Drivers should expect periodic stoppages of up to 20 minutes between 10:30 p.m. and 4 a.m. nightly.

 

I-66 West from Route 50 to Route 286

Ongoing

The HOV lane will be closed for roadway widening work.

 

I-66 East from Monument Drive to Waples Mill Road

Ongoing

The HOV lane will be closed for bridge work.

 

Route 50 East at I-66

Ramp from Route 50 East to I-66 East

Ongoing

The left lane will be closed for bridge construction.

 

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

I-66 East and West between Route 123 and Route 50

Monday, November 23, and Tuesday, November 24: 9:30 p.m. to 4:30 a.m.

I-66 East will be reduced to a single travel lane approaching Jermantown Road during the overnight hours Monday, November 23 and Tuesday, November 24 from 10 p.m. to 4:30 a.m. nightly. I-66 West will be reduced to a single travel lane approaching Jermantown Road during the overnight hours Monday, November 23 and Tuesday, November 24 from 9:30 p.m. and 4:30 a.m. nightly. Drivers should expect periodic stoppages of up to 20 minutes between 10:30 p.m. and 4 a.m. nightly.

 

Right-turn lane from Route 123 South to Rose Forest Drive

Ongoing

The right-turn lane will be closed for Verizon utility line relocation.

 

I-66 East from Blake Lane to Nutley Street

Ongoing

The HOV lane will be closed for paving operations.

 

ROUTE 243 (NUTLEY STREET) / VIENNA

Saintsbury Drive between Sayre Road and Saintsbury Place

Monday, November 23, and Tuesday, November 24: 8 a.m. to 5 p.m.

Wednesday, November 25: 8 a.m. to noon

Flagging operation for retaining wall construction.

 

Cedar Lane between Hilltop Drive and Cottage Street

Ongoing through mid-December

Cedar Lane over I-66 will be closed for demolition and reconstruction of the bridge.

 

I-66 West from Gallows Road to Vaden Drive

Ongoing

The HOV lane will be closed for paving operations.

 

I-66 East from Blake Lane to Nutley Street

Ongoing

The HOV lane will be closed for paving operations.

 

I-495 (CAPITAL BELTWAY) / DUNN LORING

I-66 East and West between Route 7 (Leesburg Pike) and Cedar Lane

Sunday, November 22, through Tuesday, November 24: 9:30 p.m. to 5 a.m.

I-66 East and West will be reduced to one travel lane approaching Gallows Road for overhead bridge work at Gallows Road. Drivers should expect periodic stoppages of up to 20 minutes between midnight and 4 a.m.

 

Ramp from 495 Express Lanes North to I-66 West

Sunday, November 22, through Tuesday, November 24: 9 p.m. to 5 a.m.

The ramp will be closed. Traffic will be detoured to I-66 East, take the exit for Route 7, stay to the left and turn left at the traffic signal, then follow signs to I-66 West.

 

I-66 West from Virginia Lane to I-495

Monday, November 23, and Tuesday, November 24: 10 p.m. to 5 a.m.

I-66 West will be reduced to a single travel lane for overhead bridge work. Drivers should expect periodic stoppages of up to 20 minutes between midnight and 4 a.m.

 

I-66 West from west of Gallows Road to Cedar Lane

Monday, November 23, and Tuesday, November 24: 9:30 p.m. to 5 a.m.

Two lanes closed for crews to shift barrier.

 

Gallows Road North and South between Belleforest Drive and Cottage Street

Monday, November 23, and Tuesday, November 24: 8:30 a.m. to 4 p.m.

Wednesday, November 25: 8 a.m. to noon

One lane will be closed for utility work.

 

I-495 North and South between Route 7 and Route 29 (Lee Highway)

Monday, November 23, and Tuesday, November 24: 10 p.m. to 5 a.m.

Three lanes will be closed for bridge construction.

 

I-66 West from Gallows Road to Vaden Drive

Ongoing

The HOV lane will be closed for paving operations.

 

I-66 East from Blake Lane to Gallows Road

Ongoing

The HOV lane will be closed for paving operations.