The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

 

ROUTE 29 / GAINESVILLE

I-66 West from Route 234 Business to Route 29 Gainesville

Ongoing

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 8 p.m. daily, three travel lanes will be open to all traffic. Between 8 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

I-66 East and West from Route 29 Gainesville to Prince William Parkway (Route 234 Bypass)

Tuesday, May 26, through Friday, May 29: 9 p.m. to 5 a.m.

Two lanes closed for overhead bridge work at University Boulevard

 

 

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 West from Route 234 Business to Route 29 Gainesville

Ongoing

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 8 p.m. daily, three travel lanes will be open to traffic. Between 8 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

Ramp from I-66 East to Route 234 Business North and South

Tuesday, May 26: 10 p.m. to 5 a.m.

The ramp will be closed for drainage installation. Traffic will directed to exit prior to the closure at Exit 44 (Route 234 Bypass) South, turn left on to Balls Ford Road to Route 234 Business.

 

Ramp from Route 234 Business South to I-66 East

Wednesday, May 27, through Friday, May 29: 8:30 p.m. to 4:30 a.m.

The spur ramp from southbound Route 234 Business to eastbound I-66 will be closed. Traffic will be directed to continue further south on Route 234 Business, stay to the left and make a u-turn at the traffic signal for Balls Ford Road, back to I-66 East.

 

I-66 West near Bull Run

Tuesday, May 26, through Friday, May 29: 11 a.m. to 12 p.m.

Temporary 15-minute stoppages of traffic for blasting operations.

 

Vandor Lane from Route 234 Business to Rest Area

Ongoing, between 7 a.m. to 5 p.m.

Flagging operation for utility work.

 

ROUTE 28 (SULLY ROAD) / CENTREVILLE

Ramp from Route 29 North and South to I-66 East

Wednesday, May 27, through Friday, May 29: midnight to 4 a.m.

The ramp will be closed for drainage works. Traffic will be directed to Route 28 to access I-66 East.

 

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Tuesday, May 26, through Friday, May 29: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West, and Route 28 North and South for blasting operations.

 

Ramp from I-66 East to Route 28 North

Nightly, through June 14

Monday through Friday: 9 p.m. to 4 a.m.

Saturday and Sunday: 9 p.m. to 6 a.m.

The ramp will be closed nightly. Traffic will be detoured farther east to Route 286 (Fairfax County Parkway) North, stay to the right for I-66 West, then follow signs to Route 28 North.

 

Ramp from I-66 West to Route 28 North

Thursday night, May 28: 9:30 p.m. to 4:30 a.m.

The ramp will be closed for sign removal. Traffic will be detoured to Route 28 South, stay to the right for Route 29 North, continue to stay to the right and follow signs to Route 28 North.

 

Route 28 North from Braddock Road to Westfields Boulevard

Tuesday, May 26, through Friday, May 29: 8 p.m. to 4:30 a.m.

Two lanes will be closed for paving.

 

Route 28 South from Westfields Boulevard to Braddock Road

Tuesday, May 26, through Friday, May 29: 8 p.m. to 6 a.m.

Two lanes will be closed for paving.

 

ROUTE 286 (FAIRFAX COUNTY PARKWAY) / FAIR LAKES

No significant impacts scheduled.

 

ROUTE 50 / FAIRFAX

Route 50 East at I-66

Ramp from Route 50 East to I-66 East

Ongoing

The left lane will be closed for bridge abutment construction and utility work.

 

I-66 West from Jermantown Road to Route 50

Ongoing

The HOV lane will be closed for bridge pier construction.

 

I-66 East from Route 50 to Jermantown

Tuesday, May 26, through Friday, May 29: 8 a.m. to 6 p.m.

The HOV lane will be closed for bridge pier construction.

 

I-66 East from Monument Drive to Waples Mill Road

Tuesday, May 26, through Friday, May 29: 9 p.m. to 5 a.m.

Three lanes will be closed for bridge construction at Waples Mill Road.

 

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

I-66 West from Jermantown Road to Route 50

Ongoing

The HOV lane will be closed for bridge pier construction.

 

I-66 East from Route 50 to Jermantown

Tuesday, May 26, through Friday, May 29: 8 a.m. to 6 p.m.

The HOV lane will be closed for bridge pier construction.

 

I-66 West between Nutley Street and Jermantown Road

Tuesday, May 26: 9 p.m. to 5 a.m.

Three lanes closed for overhead gantry removal.  Drivers should expect periodic 20-minute stoppages and slowdowns between midnight and 4 a.m.

 

I-66 East between Waples Mill Road and Route 123

Wednesday, May 27: 9 p.m. to 5 a.m.

Three lanes closed for overhead gantry removal.  Drivers should expect periodic 20-minute stoppages and slowdowns between midnight and 4 a.m.

 

I-66 East and West between Nutley Street and Jermantown Road

Thursday, May 28, and Friday, May 29: 9 p.m. to 5 a.m.

Two lanes closed on eastbound and westbound I-66 for sign removal

 

ROUTE 243 (NUTLEY STREET) / VIENNA

Cedar Lane between Hilltop Drive and Cottage Street

Ongoing, through November

Cedar Lane over I-66 will be closed for demolition and reconstruction of the bridge. 

 

I-66 West from Gallows Road to Cedar Lane

Thursday, May 28: 5 a.m. to 11 a.m., and 9:30 p.m. to 4:30 a.m.

Friday, May 29 at 9:30 p.m., through Saturday, May 30 at 11 a.m.

A single lane will be closed during the daytime hours Thursday and Saturday (5 a.m. to 11 a.m.) for bridge work. Two lanes will be closed during the overnight hours Thursday and Friday (9:30 p.m. to 5 a.m.).

 

I-66 East from Nutley Street to Cedar Lane

Thursday, May 28: 9 p.m. to 5 a.m.

Saturday, May 30 at 8:30 p.m., through noon on Sunday, May 31

Single lane closed for bridge demolition at Cedar Lane.

 

Saintsbury Drive from Vaden Drive to Blake Lane

Continuing through Friday, May 29: 7 a.m. to 5 p.m.

Flagging operation for utility work.

 

I-495 (CAPITAL BELTWAY) / DUNN LORING

Ramp from I-66 East to I-495 North

Ongoing 

The right lane of two will be closed for bridge pier construction.

 

I-66 West at I-495

Wednesday, May 27, through Friday, May 29: 9 p.m. to 5 a.m.

Single lane closed for crews to implement traffic shift. 

 

I-495 North from Route 29 to I-66

Tuesday, May 26, through Friday, May 29: 7 p.m. to 5 a.m.

Two lanes will be closed for bridge construction.

 

I-495 South from Route 7 (Leesburg Pike) to I-66

Tuesday, May 26, through Friday, May 29: 9 p.m. to 5 a.m.

Two lanes will be closed for bridge construction.