Week of May 17, 2020

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

 

ROUTE 29 / GAINESVILLE

I-66 West from Groveton Road to University Boulevard

Ramp from Prince William Parkway (Route 234 Bypass) to I-66 West

Staring 9 p.m. Friday, May 15, through noon Monday, May 18

I-66 West will be reduced to two travel lanes for paving operations.   The ramp form Prince William Parkway to I-66 West will also be closed.  Traffic will be directed to I-66 East, take the exit for northbound Route 234 Business (Sudley Road), then follow signs to I-66 West

 

I-66 West from Route 234 Business to Route 29 Gainesville

Starts Monday, April 20

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 8 p.m. daily, three travel lanes will be open to all traffic. Between 8 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 West from Groveton Road to University Boulevard

Ramp from Prince William Parkway (Route 234 Bypass) to I-66 West

Staring 9 p.m. Friday, May 15, through noon Monday, May 18

I-66 West will be reduced to two travel lanes for paving operations.   The ramp form Prince William Parkway to I-66 West will also be closed.  Traffic will be directed to I-66 East, take the exit for northbound Route 234 Business (Sudley Road), then follow signs to I-66 West.

 

I-66 West from Route 234 Business to Route 29 Gainesville

Starts Monday, April 20

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 8 p.m. daily, three travel lanes will be open to all traffic. Between 8 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

Ramp from I-66 East to Route 234 Business

Monday, May 18: 10 p.m. to 5 a.m.

The ramp will be closed for drainage installation.  Traffic will be directed to exit eastbound I-66 at Exit 44/Prince William Parkway (Route 234 Bypass) South, turn left on to Balls Ford Road to Sudley Road (Route 234 Business).

 

Ramp from Route 234 Business to I-66 East

Tuesday, May 19, through Friday, May 23: 10 p.m. to 5 a.m.

The ramp will be closed for crews to set barrier and perform drainage work. Northbound Route 234 Business traffic will be directed farther north to Route 29 North, turn right and continue past the Route 29 Centreville interchange. At the intersection with Trinity Parkway/Machen Road, stay to the left and use the left-most left-turn lane to make a U-turn at the traffic signal, then stay to the right and follow signs to I-66 East. Southbound Route 234 Business traffic will be detoured to turn right on Balls Ford Road, turn left on Miramar Drive, turn left on Coverstone Drive, and then turn left onto northbound Route 234 Business and follow the northbound detour.

 

I-66 West near Bull Run

Monday, May 18, through Friday, May 22: 10 a.m. to 11 a.m.

Temporary 15-minute stoppages of traffic for blasting operations.

 

Vandor Lane from Route 234 Business to Rest Area

Monday, Apr. 27, through Friday, May 29: 7 a.m. to 5 p.m.

Single lane, two-way traffic with flagging operation for utility work.

 

ROUTE 28 (SULLY ROAD) / CENTREVILLE

Compton Road at I-66

Monday, May 4, through Friday, May 22: 7 a.m. to 7 p.m.

Single lane, two-way traffic with flagging operation for bridge construction.

 

Ramp from Route 29 to I-66 East

Tuesday, May 19, through Thursday, May 21: 9 p.m. to 4 a.m.

The ramp will be closed for storm sewer installation.  Traffic will be directed to Route 28 to access I-66 East.

 

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Monday, May 18, through Friday, May 22: 11 a.m. to noon, and 2 p.m. to 3 p.m.

Temporary 15-minute stoppages of traffic on I-66 East and West, Route 28 North and South for blasting operations.

 

Ramp from I-66 East to Route 28 North

Sunday, May 10, through Sunday, June 14: 9 p.m. to 4 a.m.

The ramp from I-66 East to Route 28 North will also be closed nightly. Traffic will be detoured farther east to Route 286 (Fairfax County Parkway) North, stay to the right for I-66 West, then follow signs to Route 28 North.

 

Route 28 North from Braddock Road to Westfields Boulevard

Sunday, May 17, through Saturday, May 23: 8 p.m. to 4:30 a.m.

Two lanes will be closed for paving.

 

Route 28 South from Westfields Boulevard to Braddock Road

Sunday, May 17, through Saturday, May 23: 8 p.m. to 6 a.m.

Two lanes will be closed for paving.

 

Ramp from I-66 West to Route 28 North

Thursday, May 21: midnight to 4 a.m.

Temporary closure of the ramp for sign removal.  Traffic will be detoured the exit for Route 28 South, stay to the right to take the exit for Route 29 North then follow signs back to Route 28 North

 

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

No significant impacts scheduled.

 

ROUTE 50 / FAIRFAX

Route 50 East at I-66

Ramp from Route 50 East to I-66 East

Monday, Apr. 20, through Saturday, August 1

Single left lane closed for bridge abutment construction and utility work.

 

I-66 West from Jermantown Road to Route 50

Beginning 8 p.m. Monday, Mar. 30, through Friday, June 12

Single left HOV lane closed for bridge pier construction.

 

I-66 East at Route 50

Saturday, May 16: 7 a.m. to 2 p.m.

One lane closed for bridge work. 

 

I-66 East from Monument Drive to Waples Mill Road

Sunday, May 17, through Thursday, May 21: 9 p.m. to 5 p.m.

Three lanes closed for bridge construction at Waples Mill Road.

 

I-66 East from Route 50 to Jermantown Road

Sunday, May 17, through Friday, May 22: 8 a.m. to 6 p.m.

Left lane closed for bridge pier construction.

 

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

I-66 West from Jermantown Road to Route 50

Beginning 8 p.m. Monday, Mar. 30, through Friday, June 12

Single left HOV lane closed for bridge pier construction.

 

I-66 West from Route 123 to Jermantown Road

Wednesday, May 20, through Friday, May 22: 9 p.m. to 5 a.m.

Two lanes closed for geotechnical work and sign removal.

 

ROUTE 243 (NUTLEY STREET) / VIENNA

Cedar Lane from Hilltop Drive to Cottage Street

Friday, May 15 at 10 p.m.

Cedar Lane over I-66 will close for demolition and reconstruction of the bridge. 

 

I-66 West Gallows Road to Cedar Lane

Monday, May 18, through Thursday, May 22: 9 p.m. to 5 a.m.

Two lanes closed for bridge demolition

 

Ramp from Route 243 (Nutley Street) South to I-66 West

Thursday, May 21: midnight to 4 a.m.

Temporary closure of the ramp to implement lane shift on Nutley Street.  Traffic will be detoured to take the exit for I-66 East, stay to the right and exit to Nutley Street North, and then stay to the right to exit to I-66 West.

Saintsbury Drive from Vaden Drive to Blake Lane

Monday, Apr. 27, through Friday, May 15: 7 a.m. to 5 p.m.

Single lane, two-way traffic with flagging operation for utility work.

 

Sutton Road from Blake Lane to Sutton Green Court

Monday, May 4, through Monday, May 25: 8 a.m. to 6 p.m.

Single lane, two-way traffic with flagging operation for utility work.

 

I-495 (CAPITAL BELTWAY)

Ramp from I-66 East to I-495 North

Beginning Monday, April 20 at 8 p.m. 

The left lane of two will be closed for bridge pier construction.

 

I-495 North from Route 29 to I-66

Monday, Apr. 27, through Friday, May 22: 7 p.m. to 5 a.m.

Two lanes will be closed for bridge construction.

 

I-495 South from Route 7 to I-66

Tuesday, May 19, and Wednesday, May 20: 9 p.m. to 5 a.m.

Two lanes will be closed for bridge construction.