Week of March 29, 2020

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 West near Bull Run

Monday, Mar. 30, through Friday, Apr. 3: 11 a.m. to 12 p.m.

Temporary 15-minute stoppages of traffic on I-66 West for blasting operations.

I-66 West between Route 29 Centreville and Cub Run

Monday, Mar. 30, through Thursday, Apr. 2: 8 p.m. to 5 a.m.

Friday, Apr.3: 8 p.m.to 9 a.m.

Three right lanes closed for crews to install bridge beams over Cub Run.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Monday, Mar. 30, through Friday, Apr. 3: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West, Route 28 North and South for blasting operations.

I-66 West between Route 29 Centreville and Cub Run

Monday, Mar. 30, through Thursday, Apr. 2: 8 p.m. to 5 a.m.

Friday, Apr.3: 8 p.m.to 9 a.m.

Three right lanes closed for crews to install bridge beams over Cub Run.

Route 29 Centreville North and South at I-66

Turn lanes from Route 29 Centreville South to I-66 West

Monday, Mar. 30, through Friday, Apr. 3: 7 a.m. to 4 p.m.

Saturday, Apr. 4: 7 a.m. to 3 p.m.

Single lane closed on northbound and southbound Route 29 at I-66 for bridge pier construction.  The turn lanes from Route 29 South to I-66West will also be narrowed to a single lane.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

Stringfellow Road North and South from Westbrook Drive to Fair Lakes Boulevard

Monday, Mar. 30, through Friday, Apr. 3: 3 a.m. to 6 p.m.

The right lane of northbound and southbound Stringfellow Road will be closed for utility relocation.

Route 286 North and South from Lee Highway (Route 29) to Fair Lakes Parkway

Monday, Mar. 30, through Thursday, Apr. 2: 9 p.m. to 5 a.m.

Friday, Apr. 3: 10 p.m. to 8 a.m.

Two lanes closed for over head bridge demoltion of I-66 bridges over Route 286.   Drivers should expect occasional 20-minute stoppages and slowdowns along northbound Route 286.

ROUTE 50 / FAIRFAX

Route 50 East at I-66

Monday, Mar. 30, through Friday, Apr. 3: 9 a.m. to 5:30 p.m.

Single left lane closed for bridge abutment construction.

I-66 West from Route 123 to Route 50

Monday, Mar. 30, and Tuesday, Mar. 31: 8 p.m. to 5 a.m.

Three lanes closed for crews to a implement lane shift at Waples Mill Road. Drivers should expect slowdowns and periodic 20-minute stoppages between midnight and 4 a.m.

 

I-66 West from Jermantown Road to Route 50

Beginning 8 p.m. Monday, Mar. 30, through Monday, Apr. 20

Single left HOV lane on westbound I-66 closed for center bridge pier work. 

 

I-66 East from Route 50 to Jermantown Road

Monday, Mar. 30, through Friday, Apr. 3: 8 a.m. to 6:30 p.m.

Single left HOV lane on eastbound I-66 closed for center bridge pier work.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

Ramp from Route 123 North and South to I-66 East

Sunday, Mar. 29, through Friday, Apr. 3: 10 p.m. to 5 a.m.

The ramp from northbound and southbound Route 123 to I-66 East will be temporarily closed. Traffic will be detoured to exit to I-66 West, take Route 50 East, and then stay to the left and follow signs to I-66 East.

I-66 West from Jermantown Road to Route 50

Beginning 8 p.m. Monday, Mar. 30, through Monday, Apr. 20

Single left HOV lane on westbound I-66 closed for center bridge pier work. 

 

I-66 East from Route 50 to Jermantown Road

Monday, Mar. 30, through Friday, Apr. 3: 8 a.m. to 6:30 p.m.

Single left HOV lane on eastbound I-66 closed for center bridge pier work. 

                                                                                               

ROUTE 243 (NUTLEY STREET) / VIENNA

Cedar Lane from Hilltop Drive to Cottage Street

Monday, Mar. 30, through Friday, Apr. 3: 7 a.m. to 5 p.m.

Single lane, two-way traffic with flagging operation for underground waterline relocation.

I-66 East from Blake Lane to Nutley Street

Sunday, Mar. 29, through Thursday, Apr. 2: 9 p.m. to 5 a.m.

Friday, Mar. 3: 9 p.m. to 9 a.m.

Two right lanes closed for barrier wall demolition.   The eastound collector-distributor lanes at Nutley Street will also be narrowed. 

I-66 West from at Nutley Street

Monday, Mar. 30, through Friday, Apr. 3: 9 a.m. to 6:30 p.m.

Single right lane closed for paving work.  The westbound collector-distributor lanes at Nutley Street will also be narrowed.   

I-495 (CAPITAL BELTWAY)

I-495 North from Route 29 to I-66

Monday, Mar. 30, thorugh Friday, Aprl 3: 7 a.m. to 5 p.m.

Single lane closed for bridge work

I-495 North and South from Route 29 to Route 7

Wednesday, Apr. 1, and Thursday, Apr. 2: 10 p.m. to 5 a.m.

Three left lanes on northbound I-495 and two left lanes on southbound I-495 will be closed for bridge work. Drivers should expect periodic 20-minute stoppages and slowdown on between midnight and 4 a.m.