The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

Ramp from I-66 West to Route 234 Business North

Sunday, Mar. 1, through Thursday, Mar. 5: midnight to 4 a.m.

The ramp will be closed for undergound drainage and utility work.  Traffic will be detoured to the exit for Route 234 Business South, exit to southbound Route 234 Business, then turn right on Covington Drive, turn right on Miramar Drive, turn right on Balls Ford Road, and then turn left at the traffic signal to northbound Route 234 Business.

I-66 East and West at Bull Run Drive

Saturday, Mar. 7:  9 p.m. to 9 a.m.

I-66 will be reduced to a single lane in each direction under Bull Run Drive.  Two-way traffic will run on I-66 East during this period. 

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Braddock Road at Route 28

Monday, Mar. 2, through Friday, Mar. 6: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West, Route 28 North and South and on Braddock Road near Route 28 for blasting operations.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

Stringfellow Road between Fair Lakes Boulevard and Village Square Drive

Monday, Mar. 2, through Friday, Mar. 6: 9 p.m. to 3 p.m.

Friday, Mar. 6, from 9 p.m. until 3 p.m. Monday, Mar. 9

The right lane of southbound Stringfellow Road will be closed for underground utility relocation. The lane will be reopened weekdays between 3 p.m. and 9 p.m. to accommodate the evening rush. 

Route 286 South from Fair Lakes Parkway to I-66

Monday, Mar. 2, and Tuesday, Mar. 3: 9 p.m. to 5 a.m.

Two lanes closed for over head bridge demoltion of I-66 bridges over Route 286.   Drivers should expect occasional 20-minute stoppages and slowdowns along northbound Route 286.

Route 286 North from Lee Highway (Route 29) to I-66

Monday, Mar. 2, through Thursday, Mar. 5: 9 p.m. to 5 a.m.

Friday, Mar. 6: 10 p.m. to 8 a.m.

Two lanes closed for over head bridge demoltion of I-66 bridges over Route 286.   Drivers should expect occasional 20-minute stoppages and slowdowns along northbound Route 286.

ROUTE 50 / FAIRFAX

No significant traffic impacts scheduled.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

Ramp from Route 123 South to I-66 East

Sunday, Mar. 1, through Thursday, Mar. 5: midnight to 4 a.m.

The ramp will be temporarily closed utility work.  Traffic will be detoured to take the exit from southbound Route 123 to westbound I-66  to the Route 50 interchange, where they will exit onto eastbound Route 50, and then make a left-hand exit to eastbound I-66.

I-66 West from Blake Lane to Jermantown Road

Sunday, Mar. 1: 9 p.m. to 5 a.m.

Two lanes closed on westbound I-66 for bridge pier demolition.

I-66 West from Vaden Drive to Jermantown Road

Monday, Mar. 2, through Thursday, Mar. 5: 9 p.m. to 5 a.m.

Three lanes closed on westbound I-66 for bridge pier demolition and excavation.

I-66 East from Route 50 to Route 123

Monday, Mar. 2, through Thursday, Mar. 5: 9 p.m. to 5 a.m.

Two left lanes closed on eastbound I-66 for bridge pier demolition and excavation

I-66 East from I-495 to Cedar Lane

I-66 West from Route 123 to Cedar Lane

Tuesday, Mar. 3: 9 p.m. to 5 a.m.

Friday, Mar. 6, and Saturday, Mar. 7: 9 p.m. to 9 a.m.

Three left lanes closed for relocation of overhead Verizon communication line. Drivers should expect occasional 20-minute stoppages and slowdowns on eastbound and westbound I-66 between midnight and 4 a.m.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 East from I-495 to Cedar Lane

I-66 West from Route 123 to Cedar Lane

Tuesday, Mar. 3: 9 p.m. to 5 a.m.

Friday, Mar. 6, and Saturday, Mar. 7: 9 p.m. to 9 a.m.

Three left lanes closed for relocation of overhead Verizon communication line. Drivers should expect occasional 20-minute stoppages and slowdowns on eastbound and westbound I-66 between midnight and 4 a.m.

I-495 (CAPITAL BELTWAY)

I-495 North from Route 50 to I-66

Tuesday, Mar. 3, through Thursday, Mar. 5: 9 p.m. – 5 a.m.

Friday, Mar. 6: 10 p.m. to 8 a.m.

Two left lanes closed for bridge pier excavation.

I-495 South from Route 7 to I-66

Wednesday, Mar. 4: 9 p.m. to 5 a.m.

Friday, Mar. 6, and Saturday, Mar. 7: 10 p.m. to 8 a.m

Two left lanes closed for bridge pier excavation. Drivers should expect occasional 20-minute stoppages and slowdowns.

I-66 East from I-495 to Cedar Lane

I-66 West from Route 123 to Cedar Lane

Tuesday, Mar. 3: 9 p.m. to 5 a.m.

Friday, Mar. 6, and Saturday, Mar. 7: 9 p.m. to 9 a.m.

Three left lanes closed for relocation of overhead Verizon communication line. Drivers should expect occasional 20-minute stoppages and slowdowns on eastbound and westbound I-66 between midnight and 4 a.m.