The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

 

ROUTE 29 (LEE HIGHWAY) / GAINESVILLE

I-66 West from Manassas Rest Area to Route 29 Gainesville

Ongoing

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 8 p.m. daily, three travel lanes will be open to all traffic. Between 8 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 West from Manassas Rest area to Route 29 Gainesville

Ongoing

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 8 p.m. daily, three travel lanes will be open to traffic. Between 8 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Monday, July 13, through Friday, July 17: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West, and Route 28 North and South for blasting operations.

 

I-66 West from Route 28 to Route 29 Centreville

Sunday, July 12: 9 p.m. to 5 a.m.

Three lanes will be closed for crews to implement lane shifts and a 10-day closure of the HOV lane. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

 

Route 28 North at I-66

Ongoing

The right lane of Route 28 North at I-66 is closed to provide extended merge lane for the ramp from I-66 East to northbound Route 28

 

Route 28 South from Braddock Road to Route 29

Ramp from Route 28 South to I-66 West

Wednesday, July 15, and Thursday, July 16: 9 p.m. to 5 a.m.

Two lanes closed for crews to implement lane shifts.   The ramp from southbound Route 28 to I-66 West will be closed between midnight and 4 a.m. Drivers will be directed to continue farther south to Route 29 South, follow signs to I-66 West and make a left at the traffic signal to access I-66 West.

 

Route 28 North and South between I-66 and Route 29

Monday, July 13, through Friday, July 17: 9 p.m. to 5 a.m.

The left lane will be closed for demolition of the median barrier.

 

Route 28 North from I-66 to Westfields Boulevard

Ongoing

Between 8 p.m. and 4:30 a.m. nightly, two lanes will be closed for crews to implement a traffic shift and paving. Between 9 a.m. and 5 p.m. daily, one lane will be closed.

 

ROUTE 286 (FAIRFAX COUNTY PARKWAY) / FAIR LAKES

I-66 East from West Ox Road to Waples Mill Road

Sunday, July 12, through Friday, July 17: 9 p.m. to 5 a.m.

Three lanes will be closed for crews to implement a lane shift and bridge construction.

 

I-66 East from Monument Drive to Waples Mill Road

Ongoing, starting Monday, July 13 at 8 a.m.

The HOV lane will be closed for bridge pier construction.

 

ROUTE 50 / FAIRFAX

Route 50 East at I-66

Ramp from Route 50 East to I-66 East

Ongoing

The left lane will be closed for bridge abutment construction and utility work.

 

Ramp from I-66 West to Route 50 West

Monday, July 13, through Friday, July 17: 9 a.m. to 2 p.m.

The right lane of two will be closed for hauling materials.

 

I-66 West at Route 50

Continuing through Saturday, August 15

The HOV lane will be closed for bridge pier construction.

 

I-66 West from Jermantown Road to Route 50

Monday, July 13, through Thursday, July 16: 9:30 p.m. to 4:30 a.m.

Friday, July 17: 9:30 p.m. to 5:30 a.m.

Three lanes will be closed for bridge construction. 

 

I-66 East from West Ox Road to Waples Mill Road

Sunday, July 12, through Friday, July 17: 9 p.m. to 5 a.m.

Three lanes will be closed for crews to implement a lane shift and bridge construction.

 

I-66 East from Monument Drive to Waples Mill Road

Ongoing, starting Monday, July 13 at 8 a.m.

The HOV lane will be closed for bridge pier construction.

 

I-66 East from Waples Mill Road to Jermantown Road

Monday, July 13, through Friday, July 17: 8 a.m. to 6 p.m.

The HOV lane will be closed for bridge pier construction.

 

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

I-66 West from Jermantown Road to Route 50

Monday, July 13, through Thursday, July 16: 9:30 p.m. to 4:30 a.m.

Friday, July 17: 9:30 p.m. to 5:30 a.m.

Three lanes will be closed for bridge construction. 

 

I-66 East from Waples Mill Road to Jermantown Road

Monday, July 13, through Friday, July 17: 8 a.m. to 6 p.m.

The HOV lane will be closed for bridge pier construction.

 

ROUTE 243 (NUTLEY STREET) / VIENNA

Cedar Lane between Hilltop Drive and Cottage Street

Ongoing through November

Cedar Lane over I-66 will be closed for demolition and reconstruction of the bridge. 

 

Nutley Street North and South from Virginia Center Boulevard to Saintsbury Drive

Ramp from Nutley Street South to I-66 West

Monday, July 13, and Tuesday, July 14: 9 p.m. to 5 a.m.

Friday, July 17: 9 p.m. to 5 a.m.

One lane (two lanes on Friday night) closed on northbound and southbound Nutley Street for crews to implement lane shifts and long term traffic pattern changeThe ramp from southbound Nutley Street to I-66 West will be closed between midnight and 4 a.m.  Traffic will be directed further south on Nutley Street, stay to the left to make a U-turn at the signal at Saintsbury Drive, back to I-66 West.

 

I-66 West from I-495 to west of Vaden Drive

Monday, July 13, through Thursday, July 16: 9:30 p.m. to 4:30 a.m.

Friday, July 17: 9:30 p.m. to 5:30 a.m.

I-66 West will be reduced to one travel lane for bridge pier construction at Cedar Lane and bridge beam installation at Vaden Drive near the Vienna Metrorail Station. Drivers should expect periodic 30-minute stoppages nightly at Vaden Drive for crews to lift bridge beams into place.

 

I-66 East from Vaden Drive to Cedar Lane

Monday, July 13, through Friday, July 17: 9:30 p.m. to 4:30 a.m.

I-66 East will be reduced to one travel lane for demolition of the old center bridge pier located between the two Metrorail tracks at Cedar Lane.  Drivers should expect periodic 20-minute stoppages between 10 p.m. and 4 a.m.

 

I-66 East and West at Nutley Street

Tuesday, July 14: 11 p.m. to 4 a.m.

Traffic on I-66 will be stopped in both directions simultaneously three times for up to 20 minutes each for overhead utility relocation.  Stoppages will be coordinated with stoppages necessary for bridge construction on I-66 West at Vaden Drive and on I-66 East at Cedar Lane.

 

I-495 (CAPITAL BELTWAY) / DUNN LORING

I-66 West from I-495 to west of Vaden Drive

Monday, July 13, through Thursday, July 16: 9:30 p.m. to 4:30 a.m.

Friday, July 17: 9:30 p.m. to 5:30 a.m.

I-66 West will be reduced to one travel lane for bridge pier construction at Cedar Lane and bridge beam installation at Vaden Drive near the Vienna Metrorail Station. Drivers should expect periodic 30-minute stoppages nightly at Vaden Drive for crews to lift bridge beams into place.

 

Ramp from I-66 East to I-495 North

Continuing through Wednesday, July 15

The right lane of two will be closed for bridge pier construction.