Week of February 2, 2020

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 East between Bull Run Drive and Route 29 Centreville

Wednesday, Feb. 5: 9 p.m. to 5 a.m.

Three lanes closed for overhead gantry removal. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66 between midnight and 4 a.m.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Braddock Road at Route 28

Ramp from Route 28 North to I-66 East

Monday, Feb. 3, through Friday, Feb. 7: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West, Route 28 North and South and on Braddock Road near Route 28 for blasting operations. Additionally, stoppages will occur on the ramp from Route 28 North to I-66 East and on the ramp from Route 28 North to I-66 West. 

I-66 East between Bull Run Drive and Route 29 Centreville

Wednesday, Feb. 5: 9 p.m. to 5 a.m.

Three lanes closed for overhead gantry removal. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66 between midnight and 4 a.m.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

Stringfellow Road between Fair Lakes Boulevard and Village Square Drive

Monday, Feb. 3, through Friday, Feb. 7: 9 p.m. to 3 p.m.

Friday, Feb. 7, from 9 p.m. until 3 p.m. Monday, Feb. 10

The right lane of southbound Stringfellow Road will be closed for underground utility relocation. The lane will be reopened weekdays between 3 p.m. and 9 p.m. to accommodate the evening rush. 

ROUTE 50 / FAIRFAX

Ramp from Route 50 East to I-66 East

Sunday, Feb. 2: 9 p.m. to 5 a.m.

One of two lanes on the ramp from eastbound Route 50 to I-66 East closed for overhead bridge demolition at Waples Mill Road.

I-66 East from Monument Drive to Route 123

Monday, Feb. 3, through Wednesday, Feb. 5: 9 p.m. to 5 a.m.

Three lanes closed for overhead bridge demolition at Waples Mill Road and Route 123. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

Route 50 East from West Ox Road to I-66

Tuesday, Feb. 4: 9 p.m. to 5 a.m.

Two lanes closed for overhead gantry removal. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound Route 50 between midnight and 4 a.m.

I-66 East from West Ox Road to Jermantown Road

Friday, Feb. 7: 9 p.m. to 5 a.m.

Three lanes closed for overhead gantry removal. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66 between midnight and 4 a.m.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

I-66 East from Jermantown Road to Vaden Drive

Sunday, Feb. 2: 9 p.m. to 5 a.m.

Three left lanes closed for crews to implement lane shifts. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66 between midnight and 4 a.m.

I-66 East from Monument Drive to Route 123

Monday, Feb. 3, and Tuesday, Feb. 4: 9 p.m. to 5 a.m.

Three lanes closed for overhead bridge demolition at Waples Mill Road and Route 123. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

I-66 West from Nutley Street to Route 123

Monday, Feb. 3, and Tuesday, Feb. 4: 9 p.m. to 5 a.m.

Three lanes closed for overhead bridge demolition at Route 123. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

I-66 East from Waples Mill Road to Route 123

Wednesday, Feb. 5, and Thursday, Feb. 6: 9 p.m. to 5 a.m.

Overhead bridge demolition at Route 123 will require lane closures along eastbound I-66. I-66 East will be reduced to one lane between 11 p.m. and 4 a.m.. All lanes will be reopened by 5 a.m.

I-66 West at Route 123

Wednesday, Feb. 5, and Thursday, Feb. 6: 9 p.m. to 5 a.m.

Single left lane closed on westbound I-66 for overhead bridge demolition at Route 123.

I-66 East Collector-Distributor Lane at Route 123

Ramps from I-66 East to Route 123 North and South

Friday, Feb. 7, and Saturday, Feb. 8: midnight to 5 a.m.

The collector-distributor lane on eastbound I-66 to exit to northbound and southbound Route 123 will be closed for overhead bridge demolition at Route 123.   Traffic will be detoured farther east to Route 243 (Nutley Street) north, stay to the right for I-66 West, then follow signs for Route 123 North and South.  Addtionally, a single right lane on eastbound I-66 at Route 123 will be closed.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 East from Jermantown Road to Vaden Drive

Sunday, Feb. 2: 9 p.m. to 5 a.m.

Three left lanes closed for crews to implement lane shifts. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66 between midnight and 4 a.m.

I-495 (CAPITAL BELTWAY)

I-495 South at I-66

Monday, Feb. 3 and Tuesday, Feb. 4: 10 p.m. – 5 a.m.

Two left lanes closed for bridge pier work.