The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

 ROUTE 29 / GAINESVILLE

I-66 West from Route 29 from Groveton Road to University Boulevard

Monday, Dec. 9, through Saturday, Dec. 14: 9 p.m. – 5 a.m.

Three right lanes closed for demolition work on the University Boulevard bridge over I-66.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 West at Bull Run

Monday, Dec. 9, through Thursday, Dec. 12: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 West for blasting operations.

I-66 East between Sudley Road and Bull Run Rest Stop

Friday, Dec. 13: 9 p.m. to 5 a.m.

Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

 ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 East and West between Route 29 Centreville and Stringfellow Road

Ramp from Route 28 North to I-66 East

Monday, Dec. 9, through Friday, Dec. 13: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West for blasting operations. Additionally, stoppages will occur on the ramp from Route 28 North to I-66 East.

I-66 East at Route 29 Centreville

Route 29 North at Stone Road

Route 29 South at Trinity Parkway

Monday, Dec. 9, through Friday, Dec. 13: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and on Route 29 North and South for blasting operations at the Route 29 Interchange.

I-66 West between Compton Road and Bull Run Drive

Tuesday, Dec. 10: 9 p.m. to 5 a.m.

Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

 I-66 East between Compton Road and Route 28

Wednesday, Dec. 11: 9 p.m. to 5 a.m.

Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

 I-66 East between Compton Road and Route 29 Centreville

Thursday, Dec. 12: 9 p.m. to 5 a.m.

Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

Route 29 Centreville at I-66

Starting 9 p.m. Friday, Dec. 13, through 5 a.m. Monday, Dec. 16

Northbound and Southbound Route 29 will be narrowed to a single lane and northbound Route 29 traffic will be diverted to one lane on the southbound side of Route 29 at I-66.  Route 29 South will operate with single lane, two-way traffic.  All ramps to and from I-66 will be right-turn in and right-turn out only.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

Stringfellow Road between Fair Lakes Boulevard and Village Square Drive

Monday, Dec. 9, through Friday, Dec. 13: 9 p.m. to 3 p.m.

Friday, Dec. 13, from 9 p.m. until 3 p.m. Monday, Dec. 16

The right lane of southbound Stringfellow Road will be closed for underground utility relocation. The lane will be reopened weekdays between 3 p.m. and 9 p.m. to accommodate the evening rush. 

ROUTE 50 / FAIRFAX

I-66 West between Route 123 and Route 50

Monday, Dec. 9: 9 p.m. to 5 a.m.

Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

I-66 West between Route 123 and Route 50

Monday, Dec. 9: 9 p.m. to 5 a.m.

Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 West from Cedar Lane to Vaden Drive

Friday, Dec.13, and Saturday, Dec. 14: 9 p.m. to 9 a.m.

Sunday, Dec. 15: 9 p.m. to 5 a.m.

Three right lanes will be closed for crews to implement lane shifts.

Cedar Lane South between Cottage Street and Hilltop Road

Sunday, Dec. 8: 11 a.m. to 3 p.m.

The southbound lane of Cedar Lane between Cottage Street and Hilltop Road will be closed for crosswalk striping.   Two-way traffic will be maintained with flagging operations.

I-495 (CAPITAL BELTWAY)

Ramp from I-495 North to I-66 East

Monday, Dec. 9: midnight – 4 a.m.

The ramp from I-495 North to I-66 East will be closed for crews to set concrete barrier. Drivers will be directed to take the exit for I-66 West, then take the exit for southbound Nutley Street, stay to the right and follow signs to I-66 East.

Ramp from I-66 East to I-495 South Express Lanes

Wednesday, Dec. 11: 9:30 p.m. – 5 a.m.

The ramp from I-66 East to the I-495 South Express Lanes will be closed for crews to set concrete barrier.  Drivers will be directed to take the exit for the I-495 South general-purpose lanes.  

 Ramp from Gallows Road South to I-495 South

Friday, Dec. 13, and Saturday, Dec. 14: 10 p.m. to 6 a.m.

The ramp from southbound Gallows Road to I-495 South will be closed for underground utility work. Drivers will be directed to continue south on Gallows Road, stay to the left and make a U-turn under police direction at the traffic signal for I-495 North, then stay to the right and follow signs to I-495 South.