The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

I-66 West from Route 29 from Groveton Road to University Boulevard

Monday, Dec. 16, and Tuesday, Dec. 17: 9 p.m. – 5 a.m.

Three right lanes closed for demolition work on the University Boulevard bridge over I-66.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 East and West at Bull Run

Monday, Dec. 16, through Friday, Dec. 20: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West for blasting operations.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 East and West between Route 29 Centreville and Stringfellow Road

Ramp from Route 28 North to I-66 East

Monday, Dec. 16, through Friday, Dec. 20: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West for blasting operations. Additionally, stoppages will occur on the ramp from Route 28 North to I-66 East.

I-66 East at Route 29 Centreville

Route 29 North at Stone Road

Route 29 South at Trinity Parkway

Monday, Dec. 16, through Friday, Dec. 20: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and on Route 29 North and South for blasting operations at the Route 29 Interchange.

Route 29 Centreville at I-66

Starting 9 p.m. Friday, Dec. 13, through 5 a.m. Monday, Dec. 16

Route 29 will be reduced to a single lane in each direction under I-66. Two-way traffic will run on Route 29 South during this period. Drivers using ramps to and from I-66 will not be allowed to make left turns during this time.

Route 29 Centreville at I-66

Friday, Dec. 20, and Saturday, Dec. 21: 10:30 p.m. to 8 a.m.

Route 29 will be reduced to a single lane in each direction under I-66. Two-way traffic will run on Route 29 North during this period. Drivers using ramps to and from I-66 will not be allowed to make left turns during this time.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

No significant traffic impacts scheduled

ROUTE 50 / FAIRFAX

No significant traffic impacts scheduled.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

Ramp from I-66 West to Route 123 (Chain Bridge Road)

Monday, Dec. 16, and Tuesday, Dec. 17: Midnight to 4 a.m.

The ramp will be closed for utility relocation. Traffic will be detoured farther west to Route 50 East, stay to the left for I-66 East, then follow signs to Route 123.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 West from Cedar Lane to Vaden Drive

Sunday, Dec. 15: 8 p.m. to 5 a.m.

Three right lanes will be closed for crews to implement lane shifts.

I-66 West from Cedar Lane to Vaden Drive

Monday, Dec. 16, through Thursday, Dec 19: 9:30 p.m. to 5 a.m.

Friday, Dec. 20: 9:30 p.m. to 9 a.m.

Demolition of the Vaden Drive bridge pier along westbound I-66 next to the Metrorail tracks will require lane closures. I-66 West will be reduced to one lane between 11 p.m. and 4 a.m.. All lanes will be reopened by 5 a.m. on weekdays (9 a.m. on Friday PM/Saturday AM)

I-495 (CAPITAL BELTWAY)

Ramp from Gallows Road South to I-495 South

Friday, Dec. 20, and Saturday, Dec. 21: 10 p.m. to 6 a.m.

The ramp from southbound Gallows Road to I-495 South will be closed for underground utility work. Drivers will be directed to continue south on Gallows Road, stay to the left and make a U-turn under police direction at the traffic signal for I-495 North, then stay to the right and follow signs to I-495 South.