Week of April 7, 2019

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

No significant traffic impacts scheduled.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 East at Bull Run Drive

Tuesday, April 9, and Wednesday, April 10: 10 a.m. to 6 p.m.

The left lane will be closed for construction activities in the median.

I-66 West at Bull Run Drive

Tuesday, April 9, and Wednesday, April 10: 7 a.m. to 2:30 p.m.

The left lane will be closed for construction activities in the median.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

I-66 West from Route 50 to Stringfellow Road

Tuesday, April 9, through Thursday, April 11: 9 p.m. to 5 a.m.

Friday, April 12, and Saturday, April 13: 9 p.m. to 9 a.m.

Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 50 / FAIRFAX

I-66 West from Route 50 to Stringfellow Road

Tuesday, April 9, through Thursday, April 11: 9 p.m. to 5 a.m.

Friday, April 12, and Saturday, April 13: 9 p.m. to 9 a.m.

Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

Ramp from Route 123 South to I-66 West

Sunday, April 7, and Monday, April 8: Midnight to 4 a.m.

Temporary closure of the ramp. Traffic will be detoured farther south to I-66 East, stay to the right for Route 123 North, and then follow signs to I-66 West.

Route 123 North and South from White Granite Drive to Eaton Place

Monday, April 8, and Tuesday, April 9: 9 p.m. to 5 a.m.

The left lane will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 East from Blake Lane to Gallows Road

Wednesday, April 10, and Thursday, April 11: 9 p.m. to 5 a.m.

Three lanes will be closed with periodic 20-minute stoppages between midnight and 4 a.m. to remove overhead gantry upright supports.

I-495 (CAPITAL BELTWAY)