Week of April 26, 2020

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

 

ROUTE 29 / GAINESVILLE

Route 29 North and South from Heathcote Boulevard to University Boulevard

Monday, Apr. 20, through Friday, Apr. 24: 8 p.m. to 6 a.m.

Two lanes on northbound Route 29 and one lane on southbound Route 29 closed for drainage installation.

 

I-66 West from Route 234 Business to Route 29 Gainesville

Starts Monday, April 20

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 9 p.m. daily, three travel lanes will be open to all traffic. Between 9 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

I-66 West from Route 234 Business to Route 29 Gainesville

Starts Monday, April 20

Single and multi-lane closures will be implemented for extended paving operations. The HOV lane will be closed indefinitely. Between noon and 9 p.m. daily, three travel lanes will be open to all traffic. Between 9 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one travel lane open. Between 6 a.m. and noon daily, two lanes will be closed, leaving two travel lanes open.

 

I-66 West near Bull Run

Monday, Apr. 27, through Friday, May 1: 11 a.m. to 12 p.m.

Temporary 15-minute stoppages of traffic for blasting operations.

 

Vandor Lane from Route 234 Business to Rest Area

Monday, Apr. 27, through Friday, May 1: 7 a.m. to 5 p.m.

Single lane, two-way traffic with flagging operation for utility work.

 

Ramp from Route 234 to I-66 East

Wednesday, Apr. 29, and Thursday, Apr. 30: 10 p.m. to 5 a.m.

The ramp from Route 234 Business North and South to eastbound I-66 will be temporarily closed for crews to set barrier.  Traffic on northbound Route 234 will be directed to continue north to the intersection with Route 29, turn right on Route 29 and continue to the I-66/Route 29 Centreville interchange, stay to the left and continue to the intersection at Trinity Parkway/Machen Road. At the traffic signal, drivers will use the left-most turn lane only to make a U-turn onto Route 29 South, then stay to the right and follow signs to I-66 East.   Traffic on southbound Route 234 will be detoured to turn right on Balls Ford Road, turn left on Miramar Drive, turn left on Coverstone Drive, and then turn left onto northbound Route 234 to follow the detour.

 

ROUTE 28 (SULLY ROAD) / CENTREVILLE

Route 29 Centreville North and South at I-66

Turn lanes from Route 29 Centreville South to I-66 West

Monday, Apr. 27, through Friday, May 1: 7 a.m. to 4 p.m.

Saturday, May 2: 7 a.m. to 3 p.m.

A single lane will be closed on Route 29 North and South at I-66 for bridge pier construction. The turn lanes from Route 29 South to I-66 West will also be narrowed to a single lane.

 

I-66 East and West between Route 29 Centreville and Stringfellow Road

Route 28 North and South between Route 29 and Braddock Road

Monday, Apr. 27, through Friday, May 1: 11 a.m. to noon

Temporary 15-minute stoppages of traffic on I-66 East and West, Route 28 North and South for blasting operations.

 

Route 28 North from Braddock Road to Westfields Boulevard

Sunday, Apr. 27, through Tuesday, Apr. 29: 8 p.m. to 4:30 a.m.

Two lanes will be closed for paving and implementation of lane shifts.

 

Route 28 South from Westfields Boulevard to Braddock Road

Wednesday, Apr. 30, through Friday, May 1: 8 p.m. to 6 a.m.

Two lanes will be closed for paving and implementation of lane shifts.

 

Stringfellow Road South from Fair Lake Boulevard to Centreville Farms Road

Monday, Apr. 27, through Friday, May 1: 9 p.m. to 6 a.m.

Overnight closure of southbound Stringfellow Road from Fair Lakes Boulevard to Centreville Farms Road for underground utility work.   Traffic will be directed to make a left on Fair Lakes Boulevard, turn right on Fair Lakes Parkway, turn right on the ramp to Route 286 (Fairfax County Parkway) South, then take the exit for Route 29 (Lee Highway) South, and then turn right on Stringfellow Road.

 

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

Stringfellow Road South from Fair Lake Boulevard to Centreville Farms Road

Monday, Apr. 27, through Friday, May 1: 9 p.m. to 6 a.m.

Overnight closure of southbound Stringfellow Road from Fair Lakes Boulevard to Centreville Farms Road for underground utility work.   Traffic will be directed to make a left on Fair Lakes Boulevard, turn right on Fair Lakes Parkway, turn right on the ramp to Route 286 (Fairfax County Parkway) South, then take the exit for Route 29 (Lee Highway) South, and then turn right on Stringfellow Road.

 

ROUTE 50 / FAIRFAX

Route 50 East at I-66

Ramp from Route 50 East to I-66 East

Monday, Apr. 20, through Friday, July 3

Single left lane closed for bridge abutment construction and utility work.

 

I-66 West from Jermantown Road to Route 50

Beginning 8 p.m. Monday, Mar. 30, through Saturday, May 11

Single left HOV lane closed for bridge pier construction.

 

I-66 East from Route 50 to Waples Mill Road

Monday, Apr. 27, and Tuesday, Apr. 28: 9 p.m. to 5 a.m.

Two left lanes closed for bridge construction in center median.

 

I-66 East from Monument Drive to Waples Mill Road

Wednesday, Apr. 29, and Thursday, Apr. 30: 9 p.m. to 5 a.m.

Three lanes closed for overhead gantry removal.  Drivers should expect slowdowns and periodic 20-minute stoppages between midnight and 4 a.m.

 

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

I-66 West from Jermantown Road to Route 50

Beginning 8 p.m. Monday, Mar. 30, through Saturday, May 11

Single left HOV lane closed for bridge pier construction.

 

I-66 West from Route 123 to Jermantown Road

Sunday, Apr. 26, and Monday, Apr. 27: 9 p.m. to 5 a.m.

Two right lanes closed for crews to adjust barrier.   

 

Ramp form I-66 West to Route 123 North and South

Tuesday, Apr. 28: midnight to 4 a.m.

Temporary ramp closure to adjust barrier. Traffic will be detoured farther west to Route 50 East, stay to the left for I-66 East, then follow signs to Route 123 North or South.

 

ROUTE 243 (NUTLEY STREET) / VIENNA

Cedar Lane from Hilltop Drive to Cottage Street

Monday, Apr. 27, through Friday, May 1: 7 a.m. to 5 p.m.

Single lane, two-way traffic with flagging operation for underground waterline relocation.

 

Ramp from Route 243 (Nutley Street) North to I-66 East

Tuesday, Apr. 28: midnight to 4 a.m.

Temporary ramp closure to implement lane shifts and set barrier.  Traffic will be detoured to take the exit for I-66 West, stay to the right and exit to Nutley Street South, and then stay to the right to exit to I-66 East.

 

Ramp from Route 243 (Nutley Street) South to I-66 West

Wednesday, Apr. 29: midnight to 4 a.m.

Temporary ramp closure to implement lane shifts and set barrier.  Traffic will be detoured to take the exit for I-66 East, stay to the right and exit to Nutley Street North, and then stay to the right to exit to I-66 West.

 

I-66 East from Route 243 (Nutley Street) to Prosperity Avenue

Monday, Apr. 27, through Wednesday, Apr. 29: 8 p.m. to 5 a.m.

Three lanes will be closed for crews to implement lane shifts and a multi-week closure of the HOV lane.  Drivers should expect slowdowns and periodic 20-minute stoppages between midnight and 4 a.m.

 

I-66 East from Vaden Drive to Route 243 (Nutley Street)

Wednesday, Apr. 29: 8 p.m. to 5 a.m.

Two right lanes closed for crews to demolish barrier. The eastbound collector-distributor lane at Nutley Street will also be narrowed. 

 

I-66 East from Blake Lane to Route 243 (Nutley Street)

Thursday, Apr. 30, and Friday, May 1: 8 p.m. to 5 a.m.

Three lanes will be closed for crews to implement lane shifts and a multi-week closure of the HOV lane.  Drivers should expect slowdowns and periodic 20-minute stoppages between midnight and 4 a.m.

 

Saintsbury Drive from Vaden Drive to Blake Lane

Monday, Apr. 27, through Friday, May 1: 7 a.m. to 5 p.m.

Single lane, two-way traffic with flagging operation for utility work.

 

I-495 (CAPITAL BELTWAY)

Ramp from I-66 East to I-495 North

Beginning Monday, April 20 at 8 p.m. 

The left lane of two will be closed for bridge pier construction.

 

Ramp from I-495 North to I-66 West

Beginning Monday, April 20 at 8 p.m. 

The left lane of two will be closed for bridge pier construction.

 

Ramp from I-495 North to I-66 West

Monday, Apr. 27: 10 p.m. to 5 a.m.

Narrowing of the ramp for crane mobilization.  Drivers should expect slowdowns and periodic 20-minute stoppages between midnight and 4 a.m.

 

I-495 North from Route 29 to I-66

Monday, Apr. 27, through Friday, May 1: 7 a.m. to 5 p.m., and 9 p.m. to 5 a.m.

A single lane will be closed during the daytime hours (7 a.m. to 5 p.m.) for bridge work.  Two lanes will be closed during the overnight hours (9 p.m. to 5 a.m.).