Week of April 21, 2019

Upcoming Lane Closures and Traffic Changes

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

No significant traffic impacts scheduled.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

No significant traffic impacts scheduled.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

I-66 West from Jermantown Road to Monument Drive

Monday, April 22, through Wednesday, April 24: 9 p.m. to 5 a.m.

Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

I-66 East from Monument Drive to Jermantown Road

Thursday, April 25: 9 p.m. to 5 a.m.

Friday, April 26, and Saturday, April 27: 9 p.m. to 9 a.m.

Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

ROUTE 50 / FAIRFAX

I-66 West from Jermantown Road to Monument Drive

Monday, April 22, through Wednesday, April 24: 9 p.m. to 5 a.m.

Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

I-66 East from Monument Drive to Jermantown Road

Thursday, April 25: 9 p.m. to 5 a.m.

Friday, April 26, and Saturday, April 27: 9 p.m. to 9 a.m.

Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

Ramp from I-66 West to Route 123

Monday, April 22, through Saturday, April 27: Midnight to 4 a.m.

The ramp will be closed for underground utility relocation and other construction activities. Traffic will be detoured farther west to Route 50 East, use the left exit for I-66 East, then follow signs to Route 123 North or South.

ROUTE 243 (NUTLEY STREET) / VIENNA

No significant traffic impacts scheduled.

I-495 (CAPITAL BELTWAY)

No significant traffic impacts scheduled.