September 2, 2018

Crews will continue shifting travel lanes and setting up concrete barriers to create safe work zones along Interstate 66. Upcoming planned construction activities include:

  • Clearing trees and brush in established work zones inside the Route 28 and Route 123 interchanges
  • Temporarily relocating underground utilities along I-66 near Jermantown Road
  • Continuing work to widen the median between Route 123 and Blake Lane to support upcoming traffic shifts

 Upcoming Lane Closures and Traffic Changes

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the I-66 Express Mobility Partners or  Virginia 511 app.

ROUTE 234 (SUDLEY ROAD) / MANASSAS

I-66 East from Groveton Road to Bull Run Drive

Thursday, September 6: 8 p.m. to 5 a.m.

Saturday, September 8: 9 p.m. to 9 a.m.

Three left lanes closed to implement long-term lane shifts for construction.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 West from Compton Road to Bull Run Drive

Wednesday, September 5 – Thursday, September 6: 9 p.m. to 6 a.m.

Three left lanes closed to implement long-term lane shifts for construction.

I-66 West from Fairfax County Parkway (Route 286) to Route 29 Centreville

Tuesday, September 4 – Wednesday, September 5: 9 p.m. to 6 a.m.

Three left lanes closed to implement long-term lane shifts for construction.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

I-66 West from Fairfax County Parkway (Route 286) to Route 29 Centreville

Tuesday, September 4 – Wednesday, September 5: 9 p.m. to 6 a.m.

Three left lanes closed to implement long-term lane shifts for construction.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 East between Nutley Street and Gallows Road

Thursday, September 6: 9 p.m. to 5 a.m.

Friday, September 7: 9 p.m. to 9 a.m.

Three left lanes closed to implement long-term lane shifts for construction.