October 29, 2018

Upcoming Lane Closures and Traffic Changes

The following planned lane closures are expected to have significant traffic impacts.  All work is subject to change based on weather and schedule.  Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.

ROUTE 234 (SUDLEY ROAD) / MANASSAS

Ramp from Prince William Parkway (Route 234 bypass) North to I-66 West

Saturday, October 27: midnight to 4 a.m.

Temporary closure of the ramp from northbound Prince William Parkway (Route 234 bypass) to westbound I-66 between midnight and 4 a.m. Traffic will be detoured via eastbound 1-66 and northbound Sudley Road (Route 234 business) back to westbound I-66.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

I-66 West from Compton Road to Bull Run

Sunday, October 23: 8 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

I-66 West from Monument Drive to Stringfellow Road

Monday, October 29 – Tuesday, October 30: 9:30pm to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.

I-66 East from Stringfellow Road to US Route 50

Wednesday, October 31 – Thursday, November 1: 9 p.m. to 5 a.m.

Friday, November 2: 9 p.m. to 9 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

ROUTE 50 / FAIRFAX

I-66 East from Stringfellow Road to US Route 50

Wednesday, October 31 – Thursday, November 1: 9 p.m. to 5 a.m.

Friday, November 2: 9 p.m. to 9 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-66 East from US Route 50 to Route 123

Monday, October 29 – Tuesday, October 30: 11 p.m. to 4 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-66 East from Jermantown Road to Route 123

Saturday, November 3: 9 p.m. to 9 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

Ramp from Route 123 South to I-66 West

Saturday, October 27: midnight to 4 a.m.

Temporary closure of the ramp from southbound Route 123 to westbound I-66 between midnight and 4 a.m. Traffic will be detoured to the I-66 East exit from Route 123 South, then take the Route 123 North exit from I-66 East, and then take the I-66 West exit from Route 123 North.

Ramp from Route 123 North to I-66 West

Monday, October 29 – Friday, November 2: midnight to 4 a.m.

Temporary overnight closure of the ramp from northbound Route 123 (Chain Bridge Road) to westbound I-66. Traffic will be detoured to Jermantown Road, then to Rosehaven Street, to Rose Haven Drive, back to Route 123 (Chain Bridge Road) south to exit to I-66 West.

I-66 East from US Route 50 to Route 123

Monday, October 29 – Tuesday, October 30: 11 p.m. to 4 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-66 East from Jermantown Road to Route 123

Saturday, November 3: 9 p.m. to 9 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

ROUTE 243 (NUTLEY STREET) / VIENNA

I-66 East from Nutley Street to I-495

Thursday, November 1: 9 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.

I-495

I-66 East from Nutley Street to I-495

Thursday, November 1: 9 p.m. to 5 a.m.

Three lanes closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.